Question: What does lag time represent in a project schedule network? A. The amount of time an activity can be delayed without impacting the project schedule
What does lag time represent in a project schedule network?
A. The amount of time an activity can be delayed without impacting the project schedule B. The amount of time required to complete an activity C. The time between the start of one activity and the start of its successor activity D. The time between the completion of one activity and the start of its successor activity