Question: Draw a project network with the information below Draw AON network forward pass and backward pass a table showing early and late activities time and
- Draw a project network with the information below
- Draw AON network forward pass and backward pass
- a table showing early and late activities time and slack time showing the details of calculations for each activity.
- Identify the critical path. What is the maximum duration of the activity that can be delayed without impacting the critical path.
- Do you expect to receive a bonus or a penalty on this project.
| Build a garage for the Simpsons | |||
| Activity | Description | Preceding Activity | Activity Time |
| A | Pour Foundation | Note | 3 |
| B | Erect Frame | A | 4 |
| C | Roof | B | 4 |
| D | Windows | B | 1 |
| E | Doors | B | 1 |
| F | Electrical | B | 3 |
| G | Rough-in frame | C, D, E, F | 2 |
| H | Door opener | E, F | 1 |
| I | Paint | G, H | 2 |
| J | Clean up | I | 1 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock