Question: What is the difference between PERT and CPM? 4. (c) (a) CPM is designed to help plan projects with high uncertainty; PERT is designed to
What is the difference between PERT and CPM? 4. (c)
(a) CPM is designed to help plan projects with high uncertainty;
PERT is designed to determine when extra resources will profitably speed the schedule.
(b) PERT is designed to help plan projects with complex technical activities; CPM is designed to plan projects with large numbers of team members.
(c) PERT is designed to help plan projects with high uncertainty;
CPM is designed to determine when extra resources will profitably speed the schedule.
(d) PERT is designed to plan projects using a lot of contracting and outsourcing; CPM is designed to plan projects when in-house resources will be used.