Question: What is the difference between PERT and CPM? 4. (c) (a) CPM is designed to help plan projects with high uncertainty; PERT is designed to

What is the difference between PERT and CPM? 4. (c)

(a) CPM is designed to help plan projects with high uncertainty;

PERT is designed to determine when extra resources will profitably speed the schedule.

(b) PERT is designed to help plan projects with complex technical activities; CPM is designed to plan projects with large numbers of team members.

(c) PERT is designed to help plan projects with high uncertainty;

CPM is designed to determine when extra resources will profitably speed the schedule.

(d) PERT is designed to plan projects using a lot of contracting and outsourcing; CPM is designed to plan projects when in-house resources will be used.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management The Managerial Process Questions!