Question: The estimated cost for the data disposition project is $25 million. The total investment cost for each phase: Phase 1 - 32.9% Phase 2

The estimated cost for the data disposition project is $25 million. The total investment cost for each phase:

 

  • Phase 1 - 32.9%

 

  • Phase 2 – 55.6%

 

  • Phase 3 – 11.5%

 

No

Project

 

Cost in Millions $

Total

 

 

Phase 1

Phase 2

Phase 3

 

1

Defining your data and data structure

1.2

2.3

0

3.5

2

Understand how data is used

1.5

.8

.2

2.5

3

Identify data interdependencies

.8

2

.2

3

4

Link data to data holds and retention schedule

.7

1.3

.5

2.5

5

Design approaches to de-identify and dispose of data

2.7

5

.3

8

6

Develop data disposition initiatives and implement them

.5

1.5

1

3

7

Establish a road map to implement initiatives

.825

1

.675

2.5

 

 

8.225

13.9

2.875

25

 

Assuming that the total cost provided were the normal cost. The optimistic cost were under-estimated by 30%, and the pessimistic cost exceeded the normal cost by 20%. Prepare a budget using an appropriate estimation technique and justify your choice. Explain to the directors how your team will handle inaccurate estimation issues.

Step by Step Solution

3.37 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

GIVEN DATA THE COMPANY STARTS THREE PROJECTS THAT IS MENSONED PHASSES TOTAL INVESTMENT ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!