Question: What should a project manager do if they discover that additional work is needed to meet project objectives? a) Add the work to the project
What should a project manager do if they discover that additional work is needed to meet project objectives?
a) Add the work to the project scope immediately
b) Submit a change request through the Perform Integrated Change Control process
c) Reject the additional work to avoid scope creep
d) Update the project charter