Question: What should a project manager do if they identify a shortage of critical resources during the Acquire Resources process? a) Ignore the shortage and continue
What should a project manager do if they identify a shortage of critical resources during the Acquire Resources process?
a) Ignore the shortage and continue with the project
b) Document the shortage and request additional resources
c) Update the project schedule
d) Request additional funding