Question: What should a project manager do if they identify a significant resource shortage during the Estimate Activity Resources process? a) Ignore the shortage and continue
What should a project manager do if they identify a significant resource shortage during the Estimate Activity Resources process?
a) Ignore the shortage and continue with the project
b) Document the shortage and take corrective actions if necessary
c) Update the project schedule
d) Request additional resources