Question: Which closeout process involves analyzing performance, finding opportunities for improvement, and salvaging parts of the project that might be useful in the future? (a) Transfer

Which closeout process involves analyzing performance, finding opportunities for improvement, and salvaging parts of the project that might be useful in the future?

(a) Transfer

(b) Customer satisfaction review

(c) Administrative closure

(d) Lessons learned