Question: Which process involves formally authorizing the existence of a project and providing the project manager with the authority to apply organizational resources to project activities?
Which process involves formally authorizing the existence of a project and providing the project manager with the authority to apply organizational resources to project activities?
a) Identify Stakeholders
b) Plan Stakeholder Engagement
c) Develop Project Charter
d) Monitor Stakeholder Engagement