Question: Which schedule development tool does not consider the availability of the project resources, only when the work may take place in the project? A. The
Which schedule development tool does not consider the availability of the project resources, only when the work may take place in the project?
A. The critical path method B. The critical chain method C. Schedule compression D. Arrow on the node method
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts