Question: You and your project team are executing a plan to install a new piece of software for every computer within your organization. Your project team

You and your project team are executing a plan to install a new piece of software for every computer within your organization. Your project team has discovered that not all of the computers within the organization can run the new software the way they had hoped. This is an example of which one of the following?

A. Assumption B. Constraint C. Risk D. Planning