Question: Your projects primary constraint is quality. In order to make certain the project team members dont feel too pressed for time and to avoid schedule
Your project’s primary constraint is quality. In order to make certain the project team members don’t feel too pressed for time and to avoid schedule risk, you decide to use which of the following activity estimating tools?
A. Expert judgment B. Qualitatively based durations C. Reserve time D. Analogous estimating