Question: Your projects primary constraint is quality. In order to make certain the project team members dont feel too pressed for time and to avoid schedule

Your project’s primary constraint is quality. In order to make certain the project team members don’t feel too pressed for time and to avoid schedule risk, you decide to use which of the following activity estimating tools?

A. Expert judgment B. Qualitatively based durations C. Reserve time D. Analogous estimating

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management The Managerial Process Questions!