Question: Your projects primary constraint is quality. To make certain the project team members dont feel too pressed for time and to avoid schedule risk, you

Your project’s primary constraint is quality. To make certain the project team members don’t feel too pressed for time and to avoid schedule risk, you decide to use which of the following activity estimating tools?

A. Three-point estimates B. Analogous estimating C. Reserve analysis D. Parametric estimating