Question: CALCULATING BUDGET ESTIMATES USING THE LEARNING CURVE Assume you have a software project that will require the coding services of a senior programmer to complete
CALCULATING BUDGET ESTIMATES USING THE LEARNING CURVE Assume you have a software project that will require the coding services of a senior programmer to complete 14 coding sequences that are relatively similar. We know that the programmer’s learning rate is .90 and that the first coding sequence is likely to take her 15 hours to complete. Using the learning curve formula, calculate the steady state time to code these sequences