Question: Consider the resource-loading table shown here. Assume that we cannot schedule more than eight hours of work during any day of the month. a. Can

Consider the resource-loading table shown here. Assume that we cannot schedule more than eight hours of work during any day of the month.

a. Can you identify any days that involve resource conflicts?

b. How would you reconfigure the loading table to resolve these resource conflicts?

JUNE 10 11 12 15 16 17 18 19 22 23 Activity

JUNE 10 11 12 15 16 17 18 19 22 23 Activity 1 2 3 4 10 5 8 A 4 4 4 4 4] B 4 4 4 C 4 4 4 4 4] D 3 3 3 3 3 3 E 3 3 3 3 3 J F 2 2 2 2 2 2] G 4 4 4 4 24 24 25 26