Question: Which project document is used to record and track assumptions and constraints throughout the project life cycle? A. project charter B. constraints log C. stakeholder
Which project document is used to record and track assumptions and constraints throughout the project life cycle? A. project charter B. constraints log C. stakeholder analysis D. assumption log