Question: A project manager is having trouble securing programmers for her project. Every time she asks the programming manager for resources for her project, he says

A project manager is having trouble securing programmers for her project. Every time she asks the programming manager for resources for her project, he says they’re all assigned to other work. So she is constanly having to go over his head to overrule him. Which type of organixation is she working for?

A. Functional B. * Strong Matrix C. Weak Matrix D. Projectized