Question: A project managers primary responsibility is to deliver the product of the project within projectconstraints. Actions taken and changes made to the benefit of one

A project manager’s primary responsibility is to deliver the product of the project within projectconstraints. Actions taken and changes made to the benefit of one constraint could negatively affectanother. Which of the following best describes the major constraints on a project?

A. Scope, number of resources, and cost B. Scope, cost, and schedule C. * Scope, schedule, cost, quality, risk, resources, and customer satisfaction D. Schedule, cost, and number of changes