Question: A sequence of tasks that cannot be delayed without causing the project to be completed late. A. Float B. * Critical path C. Milestone D.
A sequence of tasks that cannot be delayed without causing the project to be completed late.
A. Float B. * Critical path C. Milestone D. Payback period