Question: A software developer has informed the project manager that a portion of the application development is going to take five additional days to complete. The
A software developer has informed the project manager that a portion of the application development is going to take five additional days to complete. The project manager should:
A. Inform the other project participants of the schedule change B. Change the project schedule to reflect the new completion time C. * Create a project change request D. Adjust the resource budget to account for the schedule change