Question: After discovering that some project work failed to be performed according to plan, a project manager analyzes the situation. She then presents what needs to
After discovering that some project work failed to be performed according to plan, a project manager analyzes the situation. She then presents what needs to occur to correct the problems to Austin. Austin requests a change in the project to reduce the probability of negative consequences associated with project risks. What type of change request is Austin making?
A. corrective action B. defect repair C. lessons learned D. * preventive action
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts