Question: Agile project teams do the planning at three levels named as, A. Schedule, cost, quality B. Release, iteration, retrospective. C. Release, Iteration, Daily. D. None
Agile project teams do the planning at three levels named as, A. Schedule, cost, quality B. Release, iteration, retrospective.
C. Release, Iteration, Daily.
D. None of the above.