Question: Allan is the project manager and working on project estimates. He is working on a technique that employs estimation similar to a previous project. This
Allan is the project manager and working on project estimates. He is working on a technique that employs estimation similar to a previous project. This reference estimation will work if the team and the activities in the previous project are the same. Identify the estimation technique that Allan is working on.
A. Bottom-up estimation.
B. Three-point estimation.
C. Parametric estimation.
D. Analogous estimation.