Question: As a project manager, if you notice your project progress is behind the schedule, what is the best option to do first? A. Ask senior
As a project manager, if you notice your project progress is behind the schedule, what is the best option to do first?
A. Ask senior management for more resources (e.g., staffing, finance)
B. Negotiate with customers for an extension C. * Review timesheet records to understand why this happened D. Provide incentives for staff to work overtime