Question: As an output of the Perform Quantitative Risk Analysis process, the risk register is updated. These updates generally include: A. * Prioritized list of quantified

As an output of the Perform Quantitative Risk Analysis process, the risk register is updated. These updates generally include:

A. * Prioritized list of quantified risks.

B. Qualitative analysis of the threats to ignore and opportunities to accept.

C. Checklists, corrective actions, and qualified decision trees.

D. Direction, resources, and contingency costs.