Question: Assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized
Assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes which of the following processes?
A. Perform Quantitative Risk Analysis B. Identify Risks C. Perform Qualitative Risk Analysis D. Plan Risk Management