Question: Assume previous projects in the organization have overrun their budgets consistently and tend to require more contingency reserves than in the original budget. You are
Assume previous projects in the organization have overrun their budgets consistently and tend to require more contingency reserves than in the original budget. You are striving to avoid the need for additional contingency on your project and are doing so by:
A. Involving more stakeholders in the risk identification process B. Using a process decision program chart C. Consulting the knowledge transfer system D. * Using cost/benefit analysis