Question: Assume that in Problem 9 an additional employee is available for possible assignment. The following table shows the assignment alternatives and the estimated completion times.

Assume that in Problem 9 an additional employee is available for possible assignment. The following table shows the assignment alternatives and the estimated completion times. Client Project Leader 1 2 3 Jackson 10 16 32 Ellis 14 22 40 Smith 22 24 34 Burton 14 18 36

a. What is the optimal assignment?

b. How did the assignment change compared to the best assignment possible in Problem 9? Were any savings associated with considering Burton as one of the possible project leaders?

c. Which project leader remains unassigned?