Question: Assume you and your team prepared your projects scope statement, and it was approved by your sponsor and your governance committee. However, you also need
Assume you and your team prepared your project’s scope statement, and it was approved by your sponsor and your governance committee.
However, you also need to update some project documents as an output of the Define Scope process. One example is-
A. Value engineering B. * Assumptions log C. WBS Dictionary D. Change log