Question: Cheryl is a project manager leading a conference project. She prepares a document that describes the products and services to be delivered by her team
Cheryl is a project manager leading a conference project. She prepares a document that describes the products and services to be delivered by her team to the stakeholders. She will use this document during the initiation phase to highlight the conference project objectives, assumptions, schedule, and price. What document is Cheryl preparing?
A. business case B. enterprise environment factors C. project management plan D. * project statement of work