Question: Consider the following schedule network that shows the activities in your project and their associated durations in days for question: A. A-B-C. B. * A-B-D.

Consider the following schedule network that shows the activities in your project and their associated durations in days for question:

A. A-B-C.

B. * A-B-D.

C. A-C-D.

D. A-B-C-D.