Question: Controlling procurement activities according to the procurement plan, in order to verify compliance with project objectives, is a task under what process group? A. Closing
Controlling procurement activities according to the procurement plan, in order to verify compliance with project objectives, is a task under what process group?
A. Closing B. * Monitoring & Controlling C. Executing D. Planning