Question: Decomposition of the total project work into work packages involves the following activities. A. Identifying and analyzing the deliverables and related work, Structuring and organizing
Decomposition of the total project work into work packages involves the following activities.
A. Identifying and analyzing the deliverables and related work, Structuring and organizing the wbs.
B. Decomposing the upper wbs levels into lower level detailed components.
C. Developing and assigning identification codes to the wbs components, verifying that the degree of decomposition of the deliverables is appropriate.
D. All of the above.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts