Question: Draw the node network for the following project and perform the CPM calculations: Activity Duration IPA Lag ES EF LS LF TF FF A 4
Draw the node network for the following project and perform the CPM calculations:
Activity Duration IPA Lag ES EF LS LF TF FF A 4 ——
B 9 ——
C 6 A —D 4 A ——
—
B 2 E 4 B —F 2 B, C —G 6 D ——
—
E 3 H 3 F, G —