Question: For a project with SPI = 1.60 and CPI = 2.0, what should you as the project manager do? (a) Discuss rationale with the team

For a project with SPI = 1.60 and CPI = 2.0, what should you as the project manager do?

(a) Discuss rationale with the team and take corrective actions

(b) Relax and go for a celebration because you are ahead of schedule and below cost

(c) Examine the WBS and ensure that there are no missing activities, assign additional responsibilities to individuals, rebaseline the schedule if appropriate, since the original baseline might be too conservative

(d) Do nothing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Managers Questions!