Question: For a project with SPI = 1.60 and CPI = 2.0, what should you as the project manager do? (a) Discuss rationale with the team
For a project with SPI = 1.60 and CPI = 2.0, what should you as the project manager do?
(a) Discuss rationale with the team and take corrective actions
(b) Relax and go for a celebration because you are ahead of schedule and below cost
(c) Examine the WBS and ensure that there are no missing activities, assign additional responsibilities to individuals, rebaseline the schedule if appropriate, since the original baseline might be too conservative
(d) Do nothing