Question: If the duration for Activity I changes to 4 days instead of 2 days, what is the critical path in the project case found below?
If the duration for Activity I changes to 4 days instead of 2 days, what is the critical path in the project case found below?
A. 19 days B. 25 days C. 26 days D. * 27 days