Question: If the imposed finish time in question 3 above is removed and reset to 16 and the duration of Activity H is changed to 3,

If the imposed finish time in question 3 above is removed and reset to 16 and the duration of Activity H is changed to 3, what is the late finish for Activity G?

A. -11 B. * 11 C. -13 D. 13