Question: In critical path method, slack ____ A. marks the start or completion of a task. B. is a task that must be completed. C. *

In critical path method, slack ____ A. marks the start or completion of a task.

B. is a task that must be completed.

C. * is the amount of time a task may be delayed without changing the overall project completion time.

D. is the latest time an activity can be started without delaying the entire project.