Question: In the Plan Risk Responses process, an accept strategy for a negative risk or threat indicates that the project team has decided: A. To agree

In the Plan Risk Responses process, an accept strategy for a negative risk or threat indicates that the project team has decided:

A. To agree with the project manager.

B. To eliminate a specific risk or threat, to reduce the probability and/or impact of an adverse risk event to be within acceptable threshold limits, or to pursue an opportunity actively.

C. * Not to change the project management plan to deal with a risk, or it is unable to identify any other suitable response strategy.

D. To purchase insurance, or to require performance bonds, warranties, and guarantees.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Managers Questions!