Question: In using cost-benefit analysis in the Plan Quality Management process, it can be noted that: A. The primary benefit of meeting quality requirements is the
In using cost-benefit analysis in the Plan Quality Management process, it can be noted that:
A. The primary benefit of meeting quality requirements is the reduced cost associated with project quality management activities.
B. * The primary benefits of meeting quality requirements include less rework, higher productivity, lower costs, increased stakeholder satisfaction, and increased profitability.
C. The primary cost of meeting quality requirements is the increased rework to ensure stakeholder satisfaction.
D. Quality cost can not be evaluated in relationship to the expected benefit of quality in a given project.
Step by Step Solution
There are 3 Steps involved in it