Question: ____ is a series of tasks which, if delayed, would affect the completion date of the overall project. A. Task patterns B. * Critical path
____ is a series of tasks which, if delayed, would affect the completion date of the overall project.
A. Task patterns B. * Critical path C. Work breakdown structure