Question: Major processes in developing the project time schedule are listed below.A).Activity sequencingB).Activity duration estimatingC).Schedule developmentD).Activity definitionE).Schedule controlWhat is the correct order of these processes? A.
Major processes in developing the project time schedule are listed below.A).Activity sequencingB).Activity duration estimatingC).Schedule developmentD).Activity definitionE).Schedule controlWhat is the correct order of these processes?
A. D,B,A,C,E B. * D,A,B,C,E C. D,A,C,B,E D. D,B,C,A,E