Question: Mary sets a target for the project budget during the planning phase. While executing the project, she checks to make sure she is within budget.

Mary sets a target for the project budget during the planning phase.

While executing the project, she checks to make sure she is within budget.

Mary determines that she needs to refine the scope of the project and change her timeline and costs for the project activities. Mary is using which tool to manage the cost of this project?

A. cost performance baseline B. cost of quality C. * funding limit reconciliation D. vendor bid analysis