Question: Michael is the Project Manager of a software project being developed for a large customer. A senior management executive of Michaels organization suggests Michael that
Michael is the Project Manager of a software project being developed for a large customer. A senior management executive of Michael’s organization suggests Michael that adding a new feature will be a good addition to his project. What is the best course of action for Michael?
A. Document the request and present it to change control board B. * Refuse the request as this was not part of the original scope C. Accept the request as it is being suggested by a senior member of the organization D. Consult the project sponsor