Question: On the WBS, you have decided to structure it by phases of your project. In this approach- A. * Deliverables are at the third level

On the WBS, you have decided to structure it by phases of your project. In this approach-

A. * Deliverables are at the third level B. Subcomponents are at the first levell C. Major deliverables are at the second level D. Project organizational units are at the third leve