Question: Plan schedule management has 6 processes available. Terrence is the project manager in the company named as Future Technologies. He has completed the schedule management
Plan schedule management has 6 processes available. Terrence is the project manager in the company named as Future Technologies. He has completed the schedule management processes tasks related to Define activities, Sequence activities and Estimate activity Durations. He is involved in the process of analyzing activity sequence, dependency, resource requirements, duration, and logical relationships to develop the schedule model. The process which Terrence is working on is called?
A. Control schedule.
B. Develop schedule.
C. Plan schedule management.
D. Sequence activities.