Question: Recently, Mark completed the management of a construction project. The structure cost approximately $250 per square foot to build. Mark is estimating the cost of

Recently, Mark completed the management of a construction project.

The structure cost approximately $250 per square foot to build. Mark is estimating the cost of building a new structure that is very similar this one. As a cost estimate, he will use $250 times the number of proposed square feet. Mark is relying on A. three-point B. bottom-up estimating.

C. analogous estimating D. * parametric estimating