Question: Reserve Analysis involves: A. Estimating by multiplying the quantity of work by productivity rate B. * Incorporating time buffers into the activity duration estimates C.

Reserve Analysis involves:

A. Estimating by multiplying the quantity of work by productivity rate B. * Incorporating time buffers into the activity duration estimates C. Developing project schedule with contingency reserves as a recognition of the schedule risk D. Adding resource reserves to the activity resource estimates