Question: Suppose that Suyutis management in Problem 4 likes the operational efficiency of ordering once each month and in quantities of 1000 units. How much more

Suppose that Suyuti’s management in Problem 4 likes the operational efficiency of ordering once each month and in quantities of 1000 units. How much more expensive would this policy be than your EOQ recommendation? Would you recommend in favour of the 1000-unit order quantity? Explain. What would the reorder point be if the 1000-unit quantity were acceptable?