Question: The activities performed to track, review, and regulate the execution of the project; identify any areas in which changes to the plan are required; and
The activities performed to track, review, and regulate the execution of the project; identify any areas in which changes to the plan are required; and initiate corresponding changes.
A. Initiating B. Planning C. Executing D. * Monitoring and Controlling 1756.
A. A B. * B C. C D. D